A federal judge in Alexandria said Friday she would issue a preliminary injunction blocking construction of the proposed 250-foot triumphal arch at Memorial Circle in Washington, D.C., Reuters reported. U.S. District Judge Leonie Brinkema presided over Arlington County’s case. A signed Alexandria order was not available for this update.
In a separate D.C. case, U.S. District Judge Tanya Chutkan’s signed Nov. 18 order extends the existing pause through Dec. 3 or until she rules sooner on preliminary relief. It covers construction and related site work, including excavation and roadway closures.
The National Capital Planning Commission approved the site and building plans Nov. 5. The project site is at the west end of Arlington Memorial Bridge; the Alexandria court is hearing a separate suit from Arlington County.
What the commission is
The commission is the federal government’s planning agency for the capital, with approval authority over projects on federal land in D.C. It has 12 members. Four of the seats belong to D.C.: the mayor, the chairman of the D.C. Council (the city’s legislature), and two residents the mayor appoints. The other eight are federal: the president’s three appointees, including the chair, Mark Paoletta, plus officials from Defense, Interior, and the General Services Administration, and the chairs of two congressional committees.
In July, the commission approved preliminary plans 8 to 1, with three members voting “present.” This time the vote split along federal and local lines, the AP reported.
Stats 101 moment: a lopsided score isn’t the same thing as a lopsided argument. With eight federal seats, four D.C. seats and a vote that broke along those lines, 8 to 4 tells you which seats voted which way, not how persuasive either side was. No roll call has been published yet, so treat any individual’s vote as unconfirmed.
What D.C. and Virginia say
D.C. and Virginia filed their 46-page complaint on Oct. 31 against the National Park Service and other federal defendants. It has eight counts. Five counts say the project breaks a specific law. Here’s the list: the Commemorative Works Act; a federal statute on D.C. building and memorial designs, 40 U.S.C. 8106; the Height of Buildings Act, which in most cases limits D.C. buildings to 130 feet; the National Historic Preservation Act; and the National Environmental Policy Act. The other three counts argue the approvals were arbitrary and beyond the government’s authority, and ask the court to step in.
The complaint also says westbound traffic from Memorial Bridge would drop to two lanes during construction.
D.C. and Virginia argue that once ground is broken, the government will “inflict irreparable harm on both the District and Virginia,” CBS reported. Virginia Attorney General Jay Jones called the arch an “illegal vanity project.” Council Chairman Phil Mendelson, who holds one of D.C.’s commission seats, filed a declaration supporting the suit.
The case was consolidated with the earlier lawsuit from veterans and an architectural historian, so both are before Chutkan.
What the administration says
White House spokesman Davis Ingle said the arch will be “one of the most iconic landmarks.” In court, the Justice Department argued the plaintiffs lack standing, meaning they haven’t shown the kind of injury that lets them sue, and that the challengers simply “disagree with the design.” On worries about bats at the site, it was blunter: the arch is going up “in a traffic circle, not a forest or a bat cave.” It also pointed to the Supreme Court’s White House ballroom ruling as the case that should control.
What was said at the meeting
At the meeting, Paoletta pointed to a 1925 law and called the lack of an arch a “national disgrace,” the AP reported. Commissioner Paul Ingrassia said it’s “not about politics. It’s about remembrance.”
Mendelson argued the plans weren’t finished and moved to postpone the vote to December. “We cannot approve final site and building plans until we have the final site and building plans,” he said.
What the judge did
Before the vote, Chutkan had ordered the government to tell her within one hour of any commission vote. She ruled late that night.
Her temporary restraining order, a short-term freeze while a court looks at a case, bars the Park Service from construction-related work on the arch for 14 days. “The harm is certain,” she wrote, pointing to traffic and costs D.C. and Virginia couldn’t recover. She also wrote that the “sheer improbability” of a 100-year-old statute holding that authority “indicates how far defendants must stretch.”
A restraining order isn’t a final ruling. It buys time. Whether the plaintiffs can sue at all, and whether Congress has to approve the arch, are still being fought over in the case.
Here’s why the stakes run past one arch. Back in July, Evan Cash, the Council chairman’s alternate on the commission, warned the height decision could “change the ground rules for every future federal project.” Ground rules don’t check party registration. Whoever they favor today, they apply to the next project too.
What comes next
The government still needs a work authorization from the Interior Department and a Park Service notice before building. Arlington County’s separate suit continues in federal court in Alexandria.
Next to watch: the written order in Arlington County’s case and the D.C. court’s ruling on preliminary relief. Neither path has produced a final ruling on the merits.
Related: Read our previous coverage of D.C. and Virginia’s lawsuit over the proposed arch.